Saturday, November 21, 2009

Fire on Australian oil rig delays plans to stop leak into Timor Sea

A massive fire has broken out on an Austalian oil rig and delayed plans to plug the leak that has been spilling oil into the Timor Sea since August.

The blaze started on Sunday when workers began pumping heavy mud into a leaking well casing. An estimated 400 barrels of oil a day have escaped from the hole since 21 August, threatening marine wildlife over an area ten times the size of London.

Australia's government today promised an investigation, the latest drama in a 10-week saga to plug the hole.

PTTEP Australasia, which operates the oil rig, said no one was injured and nonessential workers were evacuated after the fire broke out on the West Atlas rig and Montara wellhead platform.

Officials had planned to pour more mud into the leak on Monday in the hopes of removing the source of fuel from the fire, which was sending massive plumes of smoke into the sky. But the company said it was mixing 4,000 barrels of heavy mud, and would not be ready to pour it down the well until Tuesday.

On Sunday, PTTEP Australasia chief financial officer Jose Martins said the company doesn't know how the blaze started.

"Presently there are many unanswered questions, including what caused the fire," Martins told reporters in Perth. "Our sole focus now is the safety of all personnel, bringing the fire under control and completing the well kill."

Federal resources minister Martin Ferguson said that once the spill is contained he would launch an official inquiry. "Our requirement is to assess the cause of the accident and any lessons to be learnt, and that could lead to a change in the regulatory environment," he told Australian Broadcasting Corporation radio.

Ferguson later told reporters in Melbourne that if PTTEP was "found to have been at fault with respect to any of their responsibilities, then any potential action will be appropriately considered at the time."

The oil slick from the rig, about 150 miles off Australia's north-west coast, now stretches across thousands of milesof remote ocean. Indonesia said last week that thousands of dead fish and clumps of oil have been found drifting near its coastline.

Prime minister Kevin Rudd said today he was "deeply disturbed" at the latest turn of events on the rig, signalling the government's rising frustration that fixing the spill is taking so long.

"Do I think this is acceptable? No, I don't," Rudd told Fairfax Radio Network. "Are we angry with this company? Yes we are. Are were trying to do everything we can to get this under control? You betcha."

This is an extract from http://www.guardian.co.uk/environment/2009/nov/02/timor-sea-oil-spill-australia

Friday, November 13, 2009

Nord Stream Pipeline Logistics On Schedule

This is an extract from http://www.euro-petrole.com/ne_03_actualite_i_details.php?idNews=3715

Since the middle of October, about 30 percent of the treated pipes needed for the first line of the Nord Stream Pipeline have been in storage at marshalling yards around the Baltic Sea, where they are ready for laying. That process is due to begin in spring 2010. Nord Stream AG Project Manager for Logistics Klaus Schmidt says: "Our planning for pipe laying envisages that at least 800 kilometres of pipe, or about two thirds of the pipeline’s total 1,223 kilometres length, should be available when construction starts. This is a significant element of the demanding logistics concept, which we are now implementing according to plan."

The two lines that make up the Nord Stream Pipeline system will require a total of 200,000 pipes. Without their concrete coating, these weigh some 2.3 million tonnes, as much as 230 Eiffel towers. Some of these pipes have already been delivered by rail to Mukran on the German island of Rügen and to Kotka in Finland, where the world’s most efficient concrete coating plants have been constructed specially for Nord Stream. During a 24 hours period, these facilities apply a concrete coat which doubles the pipes’ weight. The coated pipes are then stored in Mukran and Kotka or are transhipped to one of three interim stock yards located in the Swedish ports of Karlskrona and Slite or in Hanko in Finland. Next year, when pipeline construction proceeds, the pipes will be transferred from interim stock yards on to pipelay vessels.

At the end of July 2008, Nord Stream commissioned the French company EUPEC PipeCoatings S.A. with implementation of the logistics concept. As well as the concrete coating of the pipes, this includes logistical services for the two Nord Stream pipelines. The total contract is worth 650 million Euro of which 100 million Euro represents investment in building up the infrastructure required in the Baltic Sea area. Along with the construction of the concrete coating plants, the preparation of the storage areas and the modernisation or new construction of port facilities, the project will mean the direct creation of 400 new local jobs.

Minimising transport routes – a "green" solution

The routing of the Nord Stream Pipeline across the Baltic Sea fulfils the most stringent environmental standards. Part of the logistics concept, too, was to arrange low-emission means of transport and the shortest possible distances. Compared with using already existing facilities, this will mean a saving of 95,000 tonnes of CO2 emissions for the completion of the first of the two Nord Stream lines.

After extensive analysis, Nord Stream AG selected five ports that lie close to the route of the pipeline. It means that all points on the pipe-laying path can be reached by ship within one day (a round-trip including loading and unloading). All points along the route are 100 nautical miles (185 kilometres) or less from an interim stock yard. One result of this choice is to halve the pipe delivery vessels required to three from six.

In total, 96 percent of pipe and material transportation will be undertaken in an environmentally-friendly manner by ship or rail using the shortest route possible. The pipes will be trucked only within the port areas, saving on ship bunker fuel and truck diesel, thereby reducing CO2 emissions.

The specially well-placed ports of Mukran on Rügen island and Kotka in Finland will play the key role. Located where rail and ship transport intersect, the pipes are weight coated at these ports where, alongside the project’s two largest storage yards, two concrete coating plants were constructed in short order. For example, 90 percent of the pipes for the first pipeline can be delivered by rail, with the remaining 10 percent arriving by a combination of rail and ship. Up to 15 trains a week arrive in Mukran, each one carrying 100 pipes. Each averages 12 metres in length and 12 tonnes in weight. Before they are laid on the Baltic Sea bed, they are coated with heavy concrete, increasing their weight to about 23 tonnes. The 200 personnel working in Mukran and 190 in Kotka each produce some 1,000 concrete coated pipes per week. Some of these are held in pipe storage yards at these two locations. Others are shipped from Mukran to interim stock yards at Karlskrona and Slite and from Kotka for interim storage at Hanko. They are held there awaiting final shipment to a pipelay barge. Currently, some 30,000 concrete coated pipes are ready in Mukran, Karlskrona and Kotka.

Thinking "European" benefits the environment

To preserve the environment, the materials needed for concrete coating are sourced from seven European countries, minimising delivery distances and emissions. The major part is made up of 1.38 million tonnes of magnetite delivered by MINELCO AB from Sweden. The German firm of Mibau won the contract for delivery from the Norwegian port of Narvik. The German Holcim company is supplying 370,000 tonnes of cement, with delivery via DB Schenker by rail or by ship and rail to Kotka. A further 370,000 tonnes of sand and gravel will arrive by sea from Scandinavia. Anodes for the active protection of the pipeline will be delivered by ship from Italy. Trucks will be used solely to transport small volumes of material, such as steel from Belgium, Holland and France and clearance pegs from Britain required for the wire cages used in the coating process.

The manufacture and transport of the pipes also involve several European companies. German steel pipe manufacturer EUROPIPE of Mülheim is producing 75,000 pipes for the first Nord Stream line for delivery by DB Schenker Rail Deutschland AG. The other 25,000 pipes for the first line are being produced by Russian steel firm OMK in Vyksa (350 km east of Moscow) from where they will be delivered by the Russian national railway company to Kotka. The onward transport of the concrete coated pipes from Mukran and Kotka to the interim stock yards at Karlskrona, Slite and Hanko is being undertaken by Swedish shipping company AtoB@C Shipping AB. Norway’s NorSea Group is responsible for pipe handling and storage at the three interim stock yards. Sea Terminal Sassnitz GmbH, part of the Hamburg-based BUSS Group, has taken on all logistics activities at Mukran. The same task at Kotka will be undertaken by Stella Stevedorica Oy Ltd of Kotka.

Nord Stream’s logistics concept is being successfully implemented in partnership with EUPEC PipeCoatings. Nord Stream’s logistics concept:

minimises environmental impact in the Baltic Sea region through the most economical use of resources,
benefits participating ports by investing in the long-term upgrading of their infrastructure,
boosts local economies through job creation.